TechnologyTopusko, Banovina
A Gigawatt near Topusko
A Croatian entrepreneur and U.S. investors have announced a one-gigawatt AI data centre near Topusko, valued at more than €50 billion. It would consume about one and a half times as much electricity as Zagreb. The developer aims to start construction in 2027, while amendments to the county’s land-use plan are still under review.
Simulate a day at the campusPower simulation and graphs have not been loaded. Read how the connection is planned.
- Grid connection capacity
- 1,000 MWof which around 800 MW for computers
- Annual electricity use
- 5–5.5 TWhin full power; Zagreb spends around 3.2 TWh
- New transmission lines
- 280–300 kmfour water from 400 kV and trafostin
- Announced investment
- > 50 € billionI'm the campus around 12 billion
- Residents near the site
- 165in Peck, Katinovac and the Crni Potok (2021.)
- First capacity, target year
- 2029The procedure is still waiting for changes to the plan and permissions
How would the campus get its power?A single-species schematic of the planned connection. Select an annual period and move the clock to display the sun, network and battery shares.
Three villages, 165 residents
The campus would sit south-west of Topusko, in a triangle between Pecka, Katinovac and Crni Potok. The 2021 census counted 165 residents across the three villages, just nine in Pecka.
According to HRT, investors had already bought about 1,500 hectares in the area. The announced data campus itself would cover 310 acres, about 125 hectares, with scope to expand to 450 acres, about 182 hectares. Some Croatian media reported the original figure as 310 hectares. A solar power plant, substation and battery system are also planned on Andabak’s land.
Very Andakak, the founding partner of the project, says they decided for Topusko because there they have a country where it is possible to achieve a project "that will not harm nature and the environment", and notes that Topusko is at the centre of the country. Accurate particles and layout of buildings are not published, so the campus and the purchased land on the map are only shown in the scale around the middle of the triangle.
The municipality of Topusko had 2,222 residents in the 2021 census, a third of its 1991 population. It is known for a spa with thermal springs and the ruins of a 13th-century Cistercian abbey. Earthquakes in late 2020 and early 2021 severely affected Banovina.
The border with Bosnia and Herzegovina runs about two kilometres south of the mid-triangular and the centre of Topusko is eight kilometers northeast. It is about 90 km to Zagreb.
Where the campus would beEnable layers; keep the pointer or touch the settlement for population number.
- 1,500Ha, ha.
- Land purchased according to HRT, or 15 km2
- ≈ 125Ha, ha.
- for the campus itself (310 aker), with the possibility of spreading to around 182 ha
- 30–50Ha, ha.
- for battery system only, according to the project team
- −67%
- 1991. (from 6,824 to 2,222)
As much electricity as one and a half Zagrebs
At full operation the campus would use about 5 to 5.5 terawatt-hours of electricity a year. Zagreb uses about 3.2 TWh, while end customers across Croatia bought about 17.4 TWh the previous year.
The connection force of 1,000 megawatts is greater than the power of the Krško nuclear power plant, around 700 MW. The estimates of how much of this would be the share of Croatian consumption differ depending on what it is compared to: HRT points 20 to 30 percentage, IT analyst Marko Rakar around 40 percentage, and October interview with project manager Mario Gudel indicates slightly more than a quarter.
The figures on the money are even less solid. The announcement of "more than 50 billion euros" includes equipment that the tenants should have just installed; the campus investor estimates at 12 billion euros and in Wall Street Journal The initial amount from 13.5 billions of dollars is indicated. Compared to this, all direct foreign investments in Croatia from 1993. to 2025. amounted to 56.9 billion euros.
Gigavat and terawatt-hours. Gigavat (GW) is a force, a thousand megawatts. Terravatsat (TWh) is energy: how much is spent through time. An installation that works all year with full power from 1 GW would consume 8.76 TWh. The campus would not achieve it because computers do not work all the time and would be filled in gradually.
Why so much? Graphical processors for training and running artificial intelligence models spend much more power than classic servers, and almost all of this power turns into the heat to be taken away.
Pantheon ComparedSelect the measure. The range is shown in the lighter part of the column.
Four transmission lines for one campus
The closest 400 kV line is about 40 kilometres to the north, on the transmission ring around Zagreb. The Topusko area currently has only 35 and 110 kV lines. Pantheon is seeking four 400 kV connections.
According to the connection project, a new 400 kV train station should be built at Topusko and four water lengths of 280 to 300 km, each capacity of about 1.3 GW. Dalekovod, a member of the Končar group, values to 400 to 450 million euros, and with roads and optics the investor lists more than 500 million.
The Croatian transmission system operator (HOPS) in July accepted the optimal technical solution of the connection. According to the HOPS ten-year plan, similar infrastructure would otherwise only be built 2034. and in the real script and 2039., according to ICTbusiness.
On the October 29 panel, Project Manager Mario Gudelj said that the contract's signature is expected in November. Igor Šumonja from HOPS said that the investor would pay for the construction of four lines from 400 kV and connection costs. Until November 9 there is no public signature certificate. Panel Report
The routes have not been published. According to the project manager, much of the route is followed by Tumbri – Bihac, and part of the HOPS project Lika. "Four power lines are foreseen, although one would be sufficient to provide the necessary amount of electricity," Mario Gudelj said.
Behind the number. solar power and batteries would be on the side of the campus, behind the accounting scale, so the electricity from them would be spent directly. According to the project team, the rest would take about 2 GW of solar and wind power plants, of which 80 to 90 percent would be purchased from private manufacturers in Croatia contracts for 20 years. As a reserve, as required, they would have diesel generators.
More than 5 GW. Investor claims that the new network would allow the connection of more than five gigawatts of new renewable sources, around 5.2 GW. Compared, installed production capacity in Croatia is around 6 GW.
Portable Network TodayWaters from 400 and 220 kW in Croatia and the neighborhood and distance from Topusko to the nearest.
- 4 × 400kV
- new power lines, each around 1.3 GW
- 280–300km
- Total length of new lines
- 2,000MW
- battery power, with 8,000 MWh capacity; developing Greenvolt (KKR)
- 10–12%
- annual consumption covered by its own solar power plant 500 MW
A gigawatt of electricity becomes a gigawatt of heat
Almost all the electricity that computers use turns into heat. A one-gigawatt campus would have to shed heat as fast as it consumes electricity.
As it will cool down, it has not yet been decided. The project manager identifies two possibilities: water from its own wells, with consumption "as two golf courses per year", or electricity, with slightly less efficiency. Investors say that it will not use public water or water from rivers and streams, that they have wells at five locations and that the thermal sources of Topusko will not be compromised.
Green Action in November warned of the possible consequences of thermal and underground water pumping. Gudelj is November 9 for HRT repeated that the project will not endanger public water supply and that electricity will not be collected. These are investor claims; the impact on water should be determined by environmental assessment and the effect on electricity price is not confirmed.
With the announcement, consumption of about 100 per second, seasonally, most in summer was reported. Nacional weekly estimated that the data centre of one giant with cooling evaporation spends 3.8 up to 15 million litres of water daily. The Ministry of Environmental Protection and Green Transitions in a solution from September 10 warns that pumping could drain underground water and draining hot water into streams would harm life in them.
Waste heat could, according to the project team, be used to heat greenhouses or dry agricultural products; a specific analysis with the local community has been announced.
Topusko and heat. Thermal water in Topusko springs with a temperature of up to 53 °C according to research by the University of Zagreb; the materials of the spa also state 68-72 °C. The National estimates that the natural geothermal flow of Topusko corresponds to the strength of 5-15 MW.
Microclimate. The Ministry of Solution lists a study according to which large data centres the surface area of the ground in the average heat for 2.07 °C, measured to 10 km from the facility.
How much water and heat is that?Left: daily amount of water in Olympic pools. Right: thermal power, circle surface corresponds to strength.
Water in one day
One square is an Olympic pool, 2,500 m3.
The heat to be taken
Heat power in the megawatts.
Jobs in a municipality losing population
The developer projects 3,000 construction jobs and 1,500 permanent jobs, plus about 6,000 indirect jobs. The municipality of Topusko has 2,222 residents.
The figures changed already on the day of presentation: in the morning they talked about 5,000 to 6,000 direct and indirect jobs, in the evening about 3,000 during construction and 1,500 after it. Experts are skeptical. “Data centres do not employ people”, said Marko Rakar. Nacional says that industrial models for centres from one gigawatt anticipate 100 to 300 jobs and information security expert Lucian Caric at best 1000 to 1,500, mostly technical staff.
Commissioner Ivica Kuzmić expects the municipality's revenues to rise three to four times and to keep young people busy. Construction would require thousands of workers, and Profity warns that, due to chronic shortages of labour in construction, a large part would probably come from third countries.
Not everyone sells. Family Bajić, returnees in Peck, 27 years of livestock farming and the herd have increased by ten on 150 sheep. They say that Anjabak offered them the purchase of land and houses and a replacement house, and that they were told that there was an opportunity for expropriation. When they refused, the investor, according to HRT, ordered that they would be excluded from the project.
Andakak says the idea came from an empty land: Croatia, according to him, had a million sheep, and today only a few thousand. "When you see this data, you wonder how to use this empty land and potential."
Jobs announced and municipal residentsOne point is ten people. On the left are always residents of Topusko Municipality 2021; choose to compare them.
"Only if it is feasible, for if it is only on paper, then none of it, my boys."
“I say this is worse than war.”
"The real income of Topusko municipality would increase by three to four times."
The target is 2029. Approvals are pending.
The developer’s schedule puts the start of transmission-line construction in the fourth quarter of 2027 and the first computing capacity in early 2029. Changes to the land-use plan have yet to be adopted, and the project still requires environmental assessment and permits.
The Ministry of Environmental Protection and Green Transition of September 10 ordered Sisak-Moslavina County to conduct a major assessment of the acceptability of the ecological network within the 5. the change of the spatial plan, because it cannot exclude the impact on the 11 strictly protected areas in the area, including the Blatusha and Saseva and the Koran River with caves, even though they are locations outside them. The study must contain hydrogeological and thermal models and assess the joint impact of all operations.
Mayor Ivan Celjak October 8 has launched changes in the decision on strategic environmental impact assessment. The changes would separate the area outside the construction area of the village for the campus, move part of the county road Ž3228 and provide for a power station with power lines, solar power plants and battery tanks greater than 20 MW.
Gudelj expected October 29 to complete the county procedures by the end of February or the beginning of March 2027 It is an investor assessment without the confirmed date of adoption of the change plan.
According to the Sisak.info portal, this phase could take a year to two or maybe longer. If the campus remains in the plan, the procedure itself is followed by an environmental impact study with public debate, and permits. For long-range long-distance pipeline routes following a location permit are followed by privileges or service, with a fee.
What the ministry can ask for. If the study determines the irreversible impact on the ecological network, proposals must be thrown out of the plan. Otherwise it can prescribe conditions, such as the way the campus is cooled or the largest power of the solar power plant.
Bats. The solution also mentions the hunting grounds of protected species of bats, which in search of food fly to 30 km.
Dates of the investor and deadlinesSelect how long the spatial plan changes would take. Drawn parts do not have a known duration.
- Done Letter of intent and land Letters of intent with Končar and Greenvolt, bought around 1,500 ha. Letters are not binding.
- Connection to HOPS has accepted the July Ellaborate. The contract signature has been announced for November; it has not yet been publicly confirmed.
- In progress Spacious plan Strategic assessment and main assessment for the ecological network, with public discussion.
- Didn't start Study and licenses Environmental Impact Study for the campus itself, location and construction permit, privileges.
From the announcement to the debate over water and power
What is confirmed and what has been announced
Most of the figures for Pantheon come from the developer. Letters of intent with partners are non-binding, and no tenants for the computing capacity have been publicly confirmed. Those contracts are important for financing a project of this size.
Sources
The project information is derived from statements by investors, public documents and from reports and statements published from April to November 9, 2026 Where the sources differ, ranges are given. The daily consumption model in the image 1 is illustrated and described by the image. Maps are made from the data of OpenStreetMap and Natural Earth.
- Pantheon Atlas LLC, Business Wire (April 28, 2026). Transatlantic Investment Group Announces €50 Billion AI Data Center and Innovation Campus in Croatia. Yahoo.com
- Telegram (April 27, 2026). Topusko will have a huge AI centre, the largest investment in Croatian history. telegram.hr
- Telegram (April 28, 2026). Questions that remained unresolved after the announcement of "the biggest investment in the history of Croatia". telegram.hr
- Tris (April 28, 2026). The Pantheon project changed from morning to evening “personal description”. tris.com.hr
- Energy-Storage.news (29.4.2026.). Massive new $58.5 billion AI data center for Croatia to be anchored by 8 GWh BESS. essay-news.com
- Balkan Insight (April 28, 2026). Croatia Unveils Plan for Massive “Pantheon” AI Data Centre. balkaninsight.com
- Index.hr (April 30, 2026). Family from Topusko: Andak calls us, wants to take us out. index.hr
- HRT, M. Mlinarić (May 2, 2026). What about Pantheon AI in Topusk, and what the procedure is for building. news.hr
- National, I. Grczman (May 7, 2026). Project Pantheon: which the US ambassador said out loud, which the investor acknowledged along the way and why physics does not negotiate with letters of intent. national.hr
- Nuclear Perspective (May 8, 2026). Data centres ante portas: “Pantheon” in Topusk. nuclearaperspektiva.com
- Profitaj.hr, M. Jurčić (May 12, 2026). Pantheon: an investment of the century or the largest PR project in Croatian history? profitiraj.hr
- tportal, V. Brkulj (May 20, 2026). Project of 50 billions of euros near Topusk: electricity will not accumulate and we will not use public water. tportal.hr
- ICTbusiness (May 21, 2026). The giant Pantheon accelerates the development of the Croatian transmission network for the entire decade. ictbusiness.info
- Forbes Croatia (May 2026). In 2027. building energy infrastructure for data centre near Topusk. forbes.dnuk.hr
- Index.hr, according to Hini (June 10, 2026). Add on project Pantheon: there are large underground water pools at the site of construction. index.hr
- Energypress (July 23, 2026). Adopted by EOTRP project Pantheon Ai. energypress.net
- DCD (July 2026). Pantheon Atlas security grid approval for 1GW Croatia data center. datacenterdynamics.com
- Sisak.info (September 15, 2026). Ministry has ordered: it will be necessary to prove that the planned data center Pantheon AI does not destroy the nature of Banovina. susak.info
- Bug.hr, S. Vrbanus (September 15, 2026). Due to the Pantheon AI project in Topus, the Ministry ordered the most stringent environmental impact check. bug.hr
- Hina, according to tportal and the New List (October 8, 2026). The first step to the implementation of the Pantheon Project was taken: changes to the spatial plan have been initiated and complemented. tportal.hr , novilist.hr
- Hina, according to tportal (October 9, 2026). The entrepreneur announced the Pantheon project in Topusk: “He is going according to plan”. tportal.hr
- Hina, according to the Voice of Istria (October 10, 2026). The data centre in Topusk will consume more electricity than Zagreb. glossary.hr
- Business Log (October 17, 2026). Presentation by the head of Pantheon at the Smart Industry conference. zaslovni.hr
- Hina, according to N1 (October 29, 2026). Announcement of the agreement on connection and declarations with the Green Energy Fairi panel. n1info.hr
- Green Action (November 6, 2026). Communication on action against the centre in Topusk. green-action.hr
- tportal (November 9, 2026). Civil initiative from Topusk and SDP. tportal.hr
- HRT (November 9, 2026). Leader of Pantheon's response to criticism of electricity and water. news.hr
- New list (April 2026). Andrej Plenković's statements on the Pantheon project at the Initiative Three Sea Forum. novilist.hr
- tportal (April 28, 2026). Who is Endangered? tportal.hr
- State Bureau of Statistics. Census of the population of 2021 and earlier edition, according to Wikipedia (Topusko). wikipedia.org